Andrew Chanis, P.E.

Land-use attorney of record · 2 unique cases
2
Hearings
2
Cases
2
Concluded
50.0%
Approved of concluded
2016–2023
Active
0
Since 2024

The record, at case level

Of Andrew Chanis, P.E.’s 2 unique cases, 2 have concluded — reached a Planning Commission or ZAP decision — and 1 of those ended in approval at their final hearing: 50.0%.

Counted once per case, not once per hearing: a case postponed several times before approval would otherwise read as several losses and one win.

Hearings by year

Andrew Chanis, P.E.: hearings by year2016: 1, 2017: 0, 2018: 0, 2019: 0, 2020: 0, 2021: 0, 2022: 0, 2023: 1011’16’17’18’19’20’21’221’23

Outcome distribution

Andrew Chanis, P.E.: outcomesApproved: 1 (50%), Denied: 1 (50%)50%50%Approved 1Denied 1

Hearing timeline

Hearing dateOutcomeDistrictFirm
2023-08-29ApprovedD1LJA Engineering & Surveying, Inc.
2016-08-16Denied(none)LJA Engineering & Surveying, Inc.

Firm

LJA Engineering & Surveying, Inc.

Where they practice

D1 1

Hearing-level rates, for comparison

Postponement rate vs the fieldAndrew Chanis, P: 0%, Field median: 44%Andrew Chanis, P0%Field median44%
Approval rate 50.0% — above the field (46.1%) by 3.9 pts.

At the hearing level every appearance counts, so a case postponed N times adds N postponements and one decision. Hearing-level approval-of-decided is 50.0% (vs the field’s 46.1%) and postponement is 0.0% — both far from the case-level figure above, for exactly that reason. Two stages, two denominators: these are commission-stage outcomes (approve vs. postpone/deny at the Planning Commission or ZAP hearing), not the City Council vote. Once a Commission-recommended case reaches Council it is approved in the high-90s%, so a low commission-stage approval rate reflects strategic postponement, not defeat.

Recent cases

C8-2022-0169C8-2016-2210.0A