| Hearing date | Outcome | District | Firm |
|---|---|---|---|
| 2019-11-12 | Postponed | D1 | 3443 Zen Garden LLP |
| 2019-10-08 | Postponed | D1 | 3443 Zen Garden LLP |
| 2019-08-27 | Postponed | D1 | 3443 Zen Garden LLP |
At the hearing level every appearance counts, so a case postponed N times adds N postponements and one decision. Hearing-level approval-of-decided is 0.0% (vs the field’s 46.1%) and postponement is 100.0% — both far from the case-level figure above, for exactly that reason. Two stages, two denominators: these are commission-stage outcomes (approve vs. postpone/deny at the Planning Commission or ZAP hearing), not the City Council vote. Once a Commission-recommended case reaches Council it is approved in the high-90s%, so a low commission-stage approval rate reflects strategic postponement, not defeat.